on 08-21-2007 11:15 AM
Dear Friends,
Once I create a purchase order from a purchase requisition, shall I expect the same PR in ME56 (Asssign source to PR) ?
What to do if I want to see only the PR s pending for po creation in ME56 ?
Hi Sumit,
Go to SPRO- Materials Management Purchasing - Purchase Requisition - Define Screen Layout at Document Level then double click on Field selection Key NBB
Here you can change the filed status of field <b>Indicator: requisition closed</b> from Display to Optional.
After that you can select the closed indicator in PR.
Hope it will help you.
Regards,
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In ME56,if you will enter <b>N</b> in to the field called <b>Processing Status</b> You will get list of PRs pending for PO creation.
Hope it will help you.
Regards,
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your answers, friends.
Manish, I am able to see now PRs that are 'Not Edited'.
My ultimate goal is to set the 'closed' indicator for such PRs (not edited) which are very old (year 2003-04). But I am finding the indicator 'closed' deactivated (display only) in ME52N.
Any idea why it is deactivated ?
Hi
in ME56 u can tick diff. options to obtain desired reports like
Assigned purchase requisitions
partialy ordered requisitions
closed requisitions
select desired option and run report
Vishal..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.