material parts missing

Hi Experts,

I am creating a production order and come across that there is a shortage of material, a pop up appears displaying "material parts missing". What should I do? What are the ways to find this shortage of material and How to fill this shortage?

Can any one help me out?

Thanks ,

Anukool

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 21, 2007 at 09:50 AM

    Hi,

    Please send me tcode and other inportant details regarding your problem.

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 21, 2007 at 10:11 AM

    Hi,

    In the pop-up which appears, choose mateiral shortage you will get the shortage qty of the dependent requirement of that particular material.

    In T.code OPJK (checking control) choose your order type & business function 1 & then you can do settings that,

    1.If material not available order will not be created.

    2.Order will be created even though material is not available.

    3.Use decides whether to create an order or not.

    For the shortage qty procurement proposals (purchase requisition or planned order is to be created).

    Regards,

    Senthilkumar