Hello PP Colleagues !

Can you help me to understand why the process order change dates automatically
when TECO is revoked .For example : I have a process order on March 03, 2017, When I revoke TECO and save, the dates of the process order are rescheduled automatically to this moment .

In my client it can't happen, never a old order should change dates if this has been confirmed and technical completed but it's happen.

Somebody know how to avoid this changes . Please your help.

Best regards

Accepted Solutions (1)

Accepted Solutions (1)

former_member331397
Participant
0 Kudos

Change your scheduling type 'Backward' in configuration by going through transaction 'OPU3' (Choose appropriate order type combination). Then it wont change to the current date when you revoke TECO. you can also change the scheduling type in the order manually without changing the configuration. however, you have to change the configuration if you need it long-term solution.

Thanks,
Srini