on 08-20-2007 10:50 PM
In my setup, I have configured the standard price in Material master and have maintained source list & info records.
When I do the MIRO and check the cost report in sales order, it shows me the cost which was maintained in PO(procurement cost). My requirement is irrespective of PO, the cost should always be the one from material master.
Can anyone pl suggest what are the necessary configs to be done?
Thanks
There is something in Product Cost controlling IMG that sets the Priority of Cost elements.
1= look at P.O price, if it exists
2=look at Standard Cost in MM
You will have to change the priority sequence for you purposes
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.