I am creating Purchase requisition in APO and Cif it to ECC. I want to change few date fields logic in ECC before it gets created in ECC.

Fields which I want to change in ECC : Requested date, Delivery date, Released date based on GR proc time and Pl.Delvery time.

Please suggest a way for this customization.

Accepted Solutions (0)

Answers (1)

Answers (1)

I310607
Advisor
Advisor
0 Kudos

Hello,

check the Enhancement= CIFPUR02 component EXIT_SAPLMEPI_005 in the transaction SMOD at the ERP side.

You can use user exit 'SAPLMEPI_EXIT_005' to transfer customer-specific fields from the APO system into the purchase requisition in the R/3 system (table EBAN, INCLUDE 'CI_EBANDB').

For more information, see SAP Note: 371037

Best Regards