Changing date fields in PR in ECC when it gets Cif from APO

Aug 16, 2017 at 04:08 PM

41

avatar image
Former Member

SAP APO

I am creating Purchase requisition in APO and Cif it to ECC. I want to change few date fields logic in ECC before it gets created in ECC.

Fields which I want to change in ECC : Requested date, Delivery date, Released date based on GR proc time and Pl.Delvery time.

Please suggest a way for this customization.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Gergely Kocse
Jun 04 at 01:21 PM
0

Hello,

check the Enhancement= CIFPUR02 component EXIT_SAPLMEPI_005 in the transaction SMOD at the ERP side.

You can use user exit 'SAPLMEPI_EXIT_005' to transfer customer-specific fields from the APO system into the purchase requisition in the R/3 system (table EBAN, INCLUDE 'CI_EBANDB').

For more information, see SAP Note: 371037

Best Regards

Gergely