Settlement from network to WBS-elemen of planned costs

Hi,

I can't find any transaction to support the settlement of planned costs from network to WBS-element. The only transaction I found was the settlement of planned costs from WBS-element to WBS-element.

Is there any solution to make it possible to settle the planned costs from the network to a WBS-element? We need this functionality to support the quotation of a multi sponsored service management process. Costs are planned at network level and have to be distributed to several WBS-elements that will be used for generation a quotation (using dip). The settlement using a distribution key is necessary for the distribution of the planned costs.

Regards,

Paul

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Aug 21, 2007 at 09:53 AM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      An entirely different way to solve your split billing requirement which I have done a couple times is this:

      In RRB enhancement, create a custom independent characteristic of zzvbeln which will equal the sales document number used for processing RRB. Then create a sales document with line item assigned to the WBS element and DIP profile for each sponsor. Use condition records or other mechanism to determine the percentage split amongst the funders.

  • avatar image
    Former Member
    Aug 20, 2007 at 01:45 PM

    Hi,

    It is possible if the network is of header assigned one.

    For this, 'ActvtyAcctAsgn' in OPUV (Network Type Parameters) to be unchecked.

    By using the same network type in your Project Profile, You can maintain settlement rule in your network header.

    Thanks

    Kishore

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 27, 2007 at 02:43 PM

    First settle plan cost from network to Internal order. From Internal order settle to WBS elements by %distribution. Reciever for network settlement profile will be Order and for Internal order settlement profile will be WBS element.

    Regards,

    Sudhir

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Sudhir,

      The issue is that settlement of planned costs of a network is not possible, so another process based on this will als not work.

      Regards,

      Paul

  • avatar image
    Former Member
    Aug 30, 2007 at 09:41 AM

    To all repliers,

    Thanks for you replies. I got a note from SAP that there is a special development available to settle plan costs of networks. However the use of this development will not be supported.

    Regards,

    Paul

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello,

      Could you please the name of the special development available to settle plan costs of networks?

      Thanks

  • avatar image
    Former Member
    Aug 30, 2007 at 09:49 AM

    I close the question.