Hi All,

I have alternate sequences for the material with different time durations. Which sequence the system will select while running MRP with lead time scheduling indicator?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    author's profile photo
    Former Member
    Posted on Aug 20, 2007 at 01:16 PM

    Hi Anup

    standard only it will choose,

    for alternate Routing, it will select based on lot size, if same lot size then it will take standard sequence.

    Thanks