Hi,

PRs get created automatically whenever we attach the material component to an activity.Required Document type of PRs are maintained in transaction 'OPTT'.

My Client is using three document types for Imports, Material Procurement & Services Procurement respectively & he wants all the three document types to be mapped in Project System implementation.(All other modules have been implemented long back & now IM&PS modules are being implemented)

In transaction OPTT, only one entry is possible to maintain as Document Type. Can anybody share how to maintain three Document Types?

Thanks

Kishore

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 20, 2007 at 01:27 PM

    HI Kishore

    I think you can maintain only one Document type for PR.

    Chetan.J

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 01, 2007 at 05:21 AM

    As per standard SAP, only one type we can maintain.

    But cud get by using user exits

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.