Former Member

contract case

hi all

i hav raised one contract of Rs. 10000 on vendor....

and vendor completed the work of Rs2000

and now i hav to move rest of the work on other vendor ....

how to map ths scenario in sap

sapmm

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Aug 20, 2007 at 01:46 PM

    Hi

    Raise a new contract for new vendor with target value 8000. Change the old vendor's contract by giving the latest date as validity end.

    regards

    Chetan.J