s-alr-87013558.pngHi All ,

Above error is appearing while Assigning the material to Activity . I am try to create Reservation by assigning the material to Activity . AVAC is activated , but Budget is available against the WBS .

I read all thread related to this issue but no related thread found .

Thanks ,

Virendra .

s-alr-87013558.png (99.2 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Aug 23, 2017 at 08:49 AM
0

Hi Virendra,

What error you are receiving, is it like Budget exceeding error or ? our screenshot shows only *558

Regards

Terence

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi Maria ,

Attached error is seen while saving the network , we creating only reservation by assigning the material to network activity by Cn22 . Till system shows this error . error.jpg

Thanks ,

virendra.

error.jpg (94.9 kB)
0

Hi Virendra,

As described in the message, check the cost determination log and share the screen shot.

Regards

Terence