Skip to Content
author's profile photo
Former Member

delivery with-out order reference

hi ,sapients,

Under what circumstances and scenario, delivery with-out sales order reference is created ?

thankx in advance !!

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

7 Answers

  • author's profile photo
    Former Member
    Posted on Aug 20, 2007 at 10:51 AM

    If the sales and distribution module is in R/2 and the logistics module is in R/3 then we use LO - Delivery without order reference.

    Order will be created in R/2 or any other system and delivery will be done in R/3.

    Regards

    AK

    Add comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 20, 2007 at 10:52 AM

    free samle

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 20, 2007 at 10:54 AM

    Hi,

    in case of Stock transfer delivery will create withous ref. to sales order.

    Best Regards

    Sainath

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 20, 2007 at 10:54 AM

    Hi SJ,

    Generally we create above scenario wrt Free Goods.

    Rewards If Satisfied.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 20, 2007 at 10:55 AM

    hi

    mostly this kind of situations arise when u have an old, or say regular customer who buys huge quantities sometimes is need of material on urgent basis, in such cases u create a delivery document without the reference to the sales order..

    there r other situations too.. they completely depend on the business process tie-ups..

    Reward if Useful

    Thanx & regards..

    Naren..

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 20, 2007 at 02:06 PM

    Hi,

    1. When you launch a new product at that time you give free samples to customers for product promotion.

    2. When customer requires material very urgently, no time for sales order.

    3. When scrap is sold.

    Reward points if solution helps.

    Regards,

    Allabaqsh G. Patil

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 21, 2007 at 04:13 AM

    when new product is launched, and you have to give the samples to your customer then the process is dealt by sales promotion/deal...and delivery can take place...secondly when you are having very urgent requirement from you premium customer, then it is handled through Rush Order...i think it all depends upon the scenario...other then R2-R3 example.. i mean order in one system & delivery in another system.....i don't think so it is possible to have delivery straightaway...!!

    If it is possible...do let me know how you guys have configured the scenario.

    Regards,

    N

    Add comment
    10|10000 characters needed characters exceeded