Multiple document types per Network in Purchase Requisition stage

Hi,

PRs get created automatically whenever we attach the material component to an activity.Required Document type of PRs are maintained in transaction 'OPTT'.

My Client is using three document types for Imports, Material Procurement & Services Procurement respectively & he wants all the three document types to be mapped in Project System implementation.(All other modules have been implemented long back & now IM&PS modules are being implemented)

In transaction OPTT, only one entry is possible to maintain as Document Type. Can anybody share how to maintain three Document Types?

Thanks

Kishore

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Aug 21, 2007 at 06:25 AM

    Hi Kishore

    Let me clarify one thing that Tcode:OPTT is to specify purchasing item categories(account assignment categories) and a purchasing document type for purchase requisitions in the network, this is not the area where u create new document type.

    1) u can create new document types in the IMG>Material Management >Purchasing > Purchase requisition>define document types. where in u have define the new document type with the allowed categories and link purchase requisition with the document types.

    2) U have to link this document type to the PO document type.

    3) Then go to the OPTT transaction maintain the account assignment categories for the new document type created.

    Reward points if useful

    Regards

    Murali

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi kishore

      Ur problem can be solved by using purchase info record, create a purchase info record using MM11 transaction, there u can maintain all your requirements like service or material(local or import). Call that purchase info record in the network activity. As per the settings when u save respective PR will be generated

      Reward points if useful

      Regards

      Murali

  • avatar image
    Former Member
    Dec 01, 2007 at 05:19 AM

    Got the solution with the help of user exits

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 30, 2011 at 04:29 AM

    Mr Kishore

    I am also facing the same type of problem. Please share the user exit what you have done to slove the problem.