Costing sheet

Hi all

I have created two costing sheets with seperate

costing variants, but when ever i change the percentages of overhead

or credit, it is updating in the second one also.

where now the requirement is like that, where i have to create the 40

costing sheets for the each factory for different overhead rates. How

can i do this, if the thing is happening as above mentioned.

Please tell me is there any thing i need to do, specifically for creating the

different costing sheets with different costing variants (1 to 1

basis) for calculating the OH as per the factory wise.

Thanks

Ansuman

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 20, 2007 at 09:28 AM

    Hi Ansuman,

    I believe you are using the same overhead key / overhead group for both the costing sheets. If you want to maintain different percentages for different costing sheets, then you need to maintain differeent overhead key / overhead group.

    Best REgards,

    Chandra

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 21, 2007 at 08:57 PM

    Hi Ansuman,

    when you require 2 costing sheets with 2 costing variants,and where the cost sheet is different to different plants then i hope the following solution helps out...

    The Cost sheet is assigned in the valuation variant.

    The valuation variant can be Plant Specific and like wise the Costing Variant can also be Plant Specific at the Cost Component Structure.If it is not defined as Plant Specific then it will be applicable to all the plants.

    I hope this solves your Problem..

    Regards,

    Gangadhar