on 08-20-2007 9:29 AM
Hi all
I have created two costing sheets with seperate
costing variants, but when ever i change the percentages of overhead
or credit, it is updating in the second one also.
where now the requirement is like that, where i have to create the 40
costing sheets for the each factory for different overhead rates. How
can i do this, if the thing is happening as above mentioned.
Please tell me is there any thing i need to do, specifically for creating the
different costing sheets with different costing variants (1 to 1
basis) for calculating the OH as per the factory wise.
Thanks
Ansuman
Hi Ansuman,
when you require 2 costing sheets with 2 costing variants,and where the cost sheet is different to different plants then i hope the following solution helps out...
The Cost sheet is assigned in the valuation variant.
The valuation variant can be Plant Specific and like wise the Costing Variant can also be Plant Specific at the Cost Component Structure.If it is not defined as Plant Specific then it will be applicable to all the plants.
I hope this solves your Problem..
Regards,
Gangadhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ansuman,
I believe you are using the same overhead key / overhead group for both the costing sheets. If you want to maintain different percentages for different costing sheets, then you need to maintain differeent overhead key / overhead group.
Best REgards,
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chandrasekaran
My problem is that my client want costing sheet for each plant (40 app.),so when i am try to do the same i am facing above problem
so how can i do so many costing having different OH rate,please let me know
Thanks
Ansuman
Message was edited by:
Ansuman mohanty
Message was edited by:
Ansuman mohanty
Hi Ansuman,
I think you are using the same overhead key for all the costing sheets. Now, i think the requirement to have different costing sheet for each plant needs more clarification.
If the requirement is only for the overhead rates, then you can use the common key with DO20 dependency type (Overhead Type and Plant combination) and have only one cost sheet. Remember to use this option when the base and other rows does not change.
If the Costing sheet rows is going to change for each Plant then it would be wise to have different OH keys for each plant and different Costing sheet for each plant.
Hope this helps you.
Regards
Nambi
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.