Skip to Content
avatar image
Former Member

5 steps of sap implementation

Hi Gurus,

Could you tell me the 5 steps of implementing the SAP.

Thanks & Regards

Rishabh Soni

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

8 Answers

  • avatar image
    Former Member
    Aug 20, 2007 at 05:49 AM

    Phase 1: Project Preparation - The purpose of this phase is to provide initial planning and preparation for your SAP project.

    Phase 2: Business Blueprint - The purpose of this phase is to achieve a common understanding of how the company intends to run its business within the SAP System. The result is the Business Blueprint, a detailed documentation of the results gathered during requirements workshops. The Business Blueprint document represents the business process requirements of the company. It is the agreed statement of how the company intends to run its business within the SAP System.

    Phase 3: Realization - The purpose of this phase is to implement all the business process requirements based on the Business Blueprint. The system configuration methodology is provided in two work packages: Baseline (major scope); and Final configuration (remaining scope).

    Phase 4: Final Preparation - The purpose of this phase is to complete the final preparation (including testing, end user training, system management and cutover activities) to finalize your readiness to go live. The Final Preparation phase also serves to resolve all critical open issues. On successful completion of this phase, you are ready to run your business in your live SAP System.

    Phase 5: Go Live & Support - The purpose of this phase is to move from a project-oriented, pre-production environment to live production operation.

    Additionally:

    Some additional Infomation on ASAP methodology:

    Phase 1 - Project Preparation

    Change Charter - Goals and Managementobjectives of Organizational

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 05:50 AM

    Hi

    Refer below link

    ASAPhttp://en.wikipedia.org/wiki/SAP_Implementation">ASAP>

    <b>Project Preparation</b>

    During project preparation, SAP specialists examine project

    scope, organization of the project, project standards, and

    resource availability.

    <b>Business Blueprint</b>

    SAP specialists examine more than just the status and content

    of the business blueprint document itself. They also analyze

    project standards and procedures; status reporting; project

    directing, monitoring, and controlling; and risks, issues, and

    changes.

    <b>Realization</b>

    In the area of realization, SAP specialists examine project status

    reporting; directing, monitoring, and controlling of project

    execution; and risks, issues, and changes.

    <b>Final Preparation</b>

    Examining the period immediately before go-live, SAP specialists

    ensure that the changeover runs smoothly. They focus on enduser

    training, the go-live plan, and the ongoing support strategy.

    <b>Go-Live and Support</b>

    Once the software is up and running, SAP specialists examine

    issues such as support, upgrades, benefits, application enhancements,

    lessons learned, and plans for further rollout.

    refer below link

    http://www.sapfans.com/

    and search for SAP ASAP Documentation

    Message was edited by:

    SHESAGIRI.G

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 05:51 AM

    hi,

    pl check this link :

    ASAPhttp://www.erpgenie.com/asap/roadmap.htm">ASAP>

    Thanks

    sadhu kishore

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 06:10 AM

    Hi Rishabh,

    <b>5 STEPS OF SAP IMPLEMENTATION</b>

    The ASAP methodology adheres to a specific road map that addresses the following five general phases:

    <b>1.Project Preparation:</b>

    In this step the project team is identified and mobilized, the project standards are defined, and the project work environment is set up.

    <b>2. Business Blueprint:</b>

    In this step the business processes are defined and the business blueprint document is designed.

    <b>3. Realization:</b>

    In this step the system is configured, knowledge transfer occurs, extensive unit testing is completed, and data mappings and data requirements for migration are defined.

    <b>4. Final Preparation:</b>

    In which final integration testing, stress testing, and conversion testing are conducted, and all end users are trained.

    <b>5. Go-Live and Support:</b>

    In which the data is migrated from the legacy systems, the new system is activated, and post-implementation support is provided.

    Reward points if solution helps.

    Regards,

    Allabaqsh G. Patil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 06:12 AM

    Hi Rishabh,

    give me ur id, will send a doc on ASAP.

    Regards

    Ali

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 06:24 AM

    hi,

    Basically it is done thru ASAP Methodology. the business flow of an implementation projects are

    1. Phase I - project preparation.

    2. Phase II - Business blue print - also called AS IS process

    3. Phase III - Fit gap analysis - also called IS AS process

    4. Phase IV- Realization

    5. Phase V - Go live

    6. Phase VI - Support.

    plz. reward points if it is useful.

    regards

    KR

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 07:02 AM
    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 12, 2014 at 07:33 AM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded