InfoObject PROJECT does not contain alpa-conforming value xxx

Hi,

I activate new BI 7.0 business content for 0PROJECT (info object and rules) to update the previous existing version. I can run the 0PROJECT_TEXT just fine but when I try to load the project attributes I get the alpha-conforming message from the transfer rules.

Is there a note for that somewhere? I looked but couldn't find anything.

Thanks

Suzanne

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 19, 2007 at 04:56 PM

    The error is comming because the value which is comming from data source is not alpha numeric. Either you remove alpha conversion or edit the incomming value fromDS.

    Rewad points if useful.

    Thanks

    Tripple k

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      The message the next time it failed was for a different object, I checked off the conversion box for that object and now it's running fine.

      Thanks

      Suzanne

  • avatar image
    Former Member
    Aug 19, 2007 at 05:44 PM

    The conversion box in the transfer rules was not checked off for 0project and 0project_ex once that was done and re-activated it worked fine.