Is it possible to decide the price procedure by PO type?

Hi,

Is it possible to decide the price procedure by po type, I find it is decided by purchase organization and vendor property in mater data.and I want to assign a price procedure to a special PO type.

Thanks in advance.

Regards

Lance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 20, 2007 at 03:20 AM

    Lance,

    No, this is not possible for standard POs. You have this option only for STOs. For normal POs as you have mentioned, the pricing procedure is picked up based on the combination of the <i>schema group</i> assigned to your purchasing orgs and the <i>schema group</i> that is assigned to your vendors (in the vendor master).

    If you need such a differentiation based on PO document type, then you probably have to code this requirement into the pricing routines attached to your condition types that are used in your pricing procedure.

    Hope this helps.

    H Narayan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 02:47 AM

    Dear Lance,

    Yes, the setup is at P.Org level, if you need certain condition under PO Doc Type,than you need to use user exit.

    Or maybe you can check for SAP standard for conditon combination in SAP menu :

    MM > Purchasing >master data-->Conditions.

    Regards,

    w1n