Process order wise costing table

hi..

Is there any table which contains data from KOC4 t-code. As this is the standard report, in which table this data is getting stored?

Or is there any process order wise costing tables from which i can get total rate / cost.

plzzzzzzzzzz reply

Thanx in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 20, 2007 at 03:59 AM

    hi,

    this is the table for process order- costing data

    CRCO – Costing data.

    CRHD – Header data.

    regards,

    mohan r

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 04:21 AM

    Hi

    Please find below the costing tables.

    Check whether any table suits your requirements

    COSS-activitytype cost actual

    COSP-act mat confirmation based on act consumption

    COSP-ACTUAL mat confirmation based on actual consumption

    COSL-actual and planned product quantities-FG

    COEP- CO objet-line items(by period)

    COSPD-total primary cost of GR./IR at std price and qty

    COSSD:total secondary cost

    COSB-CO object result analysis

    glpca-actual periodic overhead

    COEPB: CO object -line items variance

    COEPL: CO object-line items for activity

    regards

    Ranga