Picking time

Hi friend

In raute determinatin, we can define raute, stages and different other lead times, where we define picking and loading time.

Raj

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Aug 19, 2007 at 01:42 AM

    hi

    try in MM01 sales and general plant tab page in the column shipping data

    regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 19, 2007 at 05:23 AM

    Hi Raj,

    Please check this link as well :

    Transportation" target="_blank">http://help.sap.com/saphelp_46c/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/content.htm">Transportation and Delivery Scheduling

    i hope it will be very helpful.

    Thanks

    Sadhu Kishore

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 19, 2007 at 06:20 AM

    we will set piking and loading time in shipping point

    route--ransit time and transpoting planning time .

    based on these sstem will first will do backward scheduling from customer requested del date to arrive material avilable and others(del scheduling).

    in shiping point and route we can set in days or houres(precise scheduling)

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2007 at 01:21 PM

    The picking time and loading time is set in the shipping point. This will determine the loading deadline and the material availability deadline. You will find these dates at the schedule line level in a sales order.