In Product costing

For purchased materials I would like to use last purchase order price.

For subcontracted materials

We have multiple vendors doing same processing on same material at different rates. But for costing purpose I would like to take the highest price available in inforecord.

Can anybody suggest me a way to do this. particularly the subcontract point.

thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

In the strategy sequences you hv an option " Valuation price with user exit". Check whether this works for you and gives you choices as u desired for both material valuation and sub contracting

If the above does not work let me know - Iam thinking of other option to meet the requirement

Please assign points and gud luck

Former Member
0 Kudos

thanks

But Valuation price with user exit is available for purchased materials only. My main concern is subcontract. Further can you please guide me which user exit to use and how to use it.