on 08-17-2007 1:43 PM
Hi Gurus,
I want to change the Basic Finish date in the service order. The
system is allowing me to change it in the change mode of service order
(IW32), but after saving when I come back and see the order again, it is
showing the old date only. I want to change the Basic Finish date as
10.09.2007. Could anybody please guide?
Prassee
Hello,
I want that the user can't change the Basics date, because we have a configuration where he put this information, and if he wants change these dates, he must go in configuration.
But I don't know where I can change parameters.
Thanks for your reply.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in the serviceorder behind the basic dates you have a field for automatic update. if you tick it out the dates should not change anymore based on the operation dates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prassee,
Please check, if the scheduling type of the involved order type 'update basic date. ', if it is active, then the basic date (start & finish) is set regarding the scheduling result.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thyagarajan,
Thanks, I have already checked the same. For the order type and palanning plant, the date adjustments set as " Adjust basic date.......", but still it is not allowing me to change the basic date.
Prasanth
> hi prasanth
>
> check for you order what scheduling parameters are
> you maintained.if the Adjust shchduling is set as" DO
> not adjust basic dates:, then i think your problem
> will occur.
>
> regards
> thyagarajan