on 08-16-2007 7:27 PM
Hello,
Following is My requirement..
I DO have bulk order for the 100 Lit of bulk material. THis order is Bulk process Order.
After the bulk order created the filling process order start .
For example once above bulk process Order for 100 Lit is generated the filling process orders start executing .for example for 25 kg one filling order , 60 kg another filling order , and for rest of 15 kg one another filling order.
The filling process order needs to bve link to main Bulk process Order.
I.e. once the main bulk process order reschedule ahead by 5 days all 3 bulk process order should be reschedule automatically.
For example .
main bulk process order 1000090.
Start date : 16 Aug 2007 Finish Date 25 Aug 2007
Link Fill process order
Filling process Order 1 for 25 Lit...Start Date 25 Aug 2007 end Date 25 Aug 2007
Filling process Order 2 for 65 Lit...Start Date 25 Aug 2007 end Date 25 Aug 2007
Filling process Order 3 for 15 Lit...Start Date 25 Aug 2007 end Date 25 Aug 2007
Once the Bulk process order get reschedule to say 5 days ahead i.e. 21 Aug 2007 all three filling process Orders should reschedule automatically ..
Kindly revert back with ur thoughts.,
Thanks
Vaibhav
Hi Vaibav,
try collective order or
you can do if you need more detail then with ABAP program you can set this
Thanks
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please check the collective order concept where bulk order is parent ,filing order is child.
Regards,
Irshad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.