Hello,

Following is My requirement..

I DO have bulk order for the 100 Lit of bulk material. THis order is Bulk process Order.

After the bulk order created the filling process order start .

For example once above bulk process Order for 100 Lit is generated the filling process orders start executing .for example for 25 kg one filling order , 60 kg another filling order , and for rest of 15 kg one another filling order.

The filling process order needs to bve link to main Bulk process Order.

I.e. once the main bulk process order reschedule ahead by 5 days all 3 bulk process order should be reschedule automatically.

For example .

main bulk process order 1000090.

Start date : 16 Aug 2007 Finish Date 25 Aug 2007

Link Fill process order

Filling process Order 1 for 25 Lit...Start Date 25 Aug 2007 end Date 25 Aug 2007

Filling process Order 2 for 65 Lit...Start Date 25 Aug 2007 end Date 25 Aug 2007

Filling process Order 3 for 15 Lit...Start Date 25 Aug 2007 end Date 25 Aug 2007

Once the Bulk process order get reschedule to say 5 days ahead i.e. 21 Aug 2007 all three filling process Orders should reschedule automatically ..

Kindly revert back with ur thoughts.,

Thanks

Vaibhav

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Vaibav,

try collective order or

you can do if you need more detail then with ABAP program you can set this

Thanks

Bala

Former Member
0 Kudos

Dear,

Please check the collective order concept where bulk order is parent ,filing order is child.

Regards,

Irshad