One More workitem is created even if the approver approves the PR

Hi All,

When a PR is created based on the release statergy the approver is found and a decision making workitem is sent to the approver where he can approver or reject or consult or transfer the PR.

When the approver approves the PR a workitem is sent to the next approver and one more workitem is getting created in the 1st approvers inbox i dont know why it is happening.

Kindly help me in this issue.

Note : i have created a new task for the decision making and i made the task as general task.

Regards

Balaji E.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Aug 17, 2007 at 04:15 AM

    Check the agent you have assigned. I think you might have mentioned the Ist level approcver with the second level approver. Try to approve the PR from 2nd levels inbox. Check the Workflow Log from SWIA Transaction Code.

    <b>Please reward points if useful</b>

    Thanks

    Arghadip

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Arghadip,

      Thanks for your reply. Since i am using user decision, i am assinging the agent as an expression. I checked the log there only the second approvers userid is mentioned not the first one's.

      kindly help me.

      Regards,

      Balaji E.

  • avatar image
    Former Member
    Aug 17, 2007 at 06:04 AM

    Are your approvers in a multiline element ? then try unchecking the advance with dialouge check box in the control tab.

    onwe more thing can be tried. Put the first approver in the excluded agent if u can .

    Hope this helps

    Anuj Sethi

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 17, 2007 at 09:17 AM

    Hi BK,

    is there a step before you send the workitem to Agents?

    2 things to check.

    1) have you assigned it as general task or any other agent assignment.

    2) check whether its a dialog step (if not a dialog, make it background)

    Hope it helps.

    Aditya

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Check the 'other' tab of the decision task. The multiline element should NOT have an entry in it. I think we might be dealing with parallel process.

      and also I hope the loop has a container element increasing the index.