what is the roll of T code ip24,& what is the roll of SCAT process ,how the measuring point report uploaded through SCAT

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Aug 16, 2007 at 09:47 AM

    hi

    ip24 is used for list display for maitnenance plan which you will schedule based on the overview.

    regards

    thyagarajan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 16, 2007 at 09:56 AM

    Hi,

    IP24 is to check the maintenance plan schedule.

    Refer to

    How SCAT is useful

    Regards

    Bala