Sales Orders - Availability Checks

Hi,

I would like to have functionality where in "availability check" will only confirm if the delivery date is less than "x" (say 7 days). i.e, if we get an order which has delivery date more than a 1 week, i don't want to confirm it now and take away the stock.

I expect the same thing to happen during bop.

Any hints / tips to implement this.

Thanks,

Ramesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Aug 16, 2007 at 08:40 AM

    use RLT 7 days

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 16, 2007 at 08:48 AM

    You can do this type of check useing the replenishment lead time cotrol you can maitian 7 dayes

    In Customizing, you define whether the availability for a combination of checking group and checking rule is checked with or without the replenishment lead time.

    The replenishment lead time is the time necessary to provide a material either by in-house production or by external procurement:

    For external procurement, the replenishment lead time consists of the purchasing department processing time, planned delivery time, and goods receipt processing time - in the same way as for forward scheduling in MRP. The ATP check only includes the planned delivery time.

    For in-house production, the system checks whether the total lead time is maintained in the material master (MRP 2 view). This is the estimated production time for a material, including all production levels from raw material procurement to final assembly.

    If the total replenishment time is maintained then this is included in the ATP check.

    If only the in-house production time is maintained and not this total replenishment time, then the in-house production time is included in the ATP check.

    If the total replenishment time and the in-house production time are maintained, then the total replenishment lead time is included in the ATP check.

    All times are specified in number of days. The only exception is the planned delivery time; this is specified in calendar days.

    Features

    You can choose whether or not the replenishment lead time is taken into consideration in the availability check:

    If the replenishment lead time is taken into consideration, it has the following consequences:

    The availability is checked only for requirements within the replenishment lead time. Requirements outside the replenishment lead time are considered to be available as the system assumes that these materials can be provided by planning within the replenishment lead time.

    If you do not want to work with infinite quantities, you can use the Availability Check Against Allocations.

    If a requirement cannot be covered by receipts, the end of the replenishment lead time is the earliest date that the material can be confirmed.

    If the replenishment lead time is not taken into consideration, the availability is checked for each requirement time without taking the replenishment lead time into consideration.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Transaction SMOD, , type in the userexit and click documentation.

      Wenn Sie diese User-Exits nutzen wollen, nehmen Sie bitte Kontakt mit der 
      SAP-Entwicklungsabteilung auf. 

      "If you want to use these exits, please contact the SAP development"

      As I said, these exits are not for the faint if heart. But interesting is the internal table MDVEX, there is no direct connection between the requirement and the result, but you are lucky, because you are interested in dates only, so just set all quantities after today + 7 to 0 and go ahead.

      Matthias

  • avatar image
    Former Member
    Aug 16, 2007 at 02:17 PM

    Hi,

    Try using the replenishment lead time as '7' days.

    Reward if helps.

    Regards,

    Allabaqsh G. Patil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 27, 2011 at 04:24 PM

    ANSWERED

    Add comment
    10|10000 characters needed characters exceeded