Funds management

Hi,

We implement Funds Management and our customer has two different budget with different commitment items. We have payment budget. For one budget it is necessary to have availability control, but for another budget we not need control. How to do this, because if i activated availability control for payment budget the availability control works for all payment budget.

SAP 78

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Aug 20, 2007 at 03:53 AM

    Path for Set up Availability Control Again

    SPRO - Controllin ---Internal Orders -Budget and Availability Control Set Availability Control Again.

    In this IMG activity, you reconstruct all the data for availability

    control. The assigned values are recalculated and references are created

    to the objects that have budget.

    The new budget profile settings are copied into the budget table.

    Recommendation

    SAP recommends that you reconstruct the PS Info Database with

    transaction CJEN before activating availability control

    Activities

    Carry out this step if:

    1. you install a new release

    2. you haved changed the availability control settings in the budget

    profile (e.g. from overall to annual values)

    3. you have changes the tolerance limits for availability control

    4. you have defined exempt cost elements - that is, cost elements which

    are not subject to availability control

    5. you have changed the order update settings for orders for projects

    6. you suspect errors in the data - for example, in objects from older

    releases or after incorporating corrections relating to budgeting or

    availability control

    I think so its fullfill your reqiuerment, if its full fill replay same.

    Regards

    Rama Mohan

    09920053146

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.