Skip to Content
avatar image
Former Member

Requirement quantity of component should be calculated as per planned order quantity after MRP

Hi All,

Our Requirement is:

In BOM the base quantity for header material(X) is 1000 nos.

component(A) quantity is 4nos.

component(B) quantity is 2nos.

Demand for material X for month of August is 100.

After MRP, planned order should have component quantity for component A and Component B as 400nos. and 200nos respectively(Multiple of planned order). But the component quantity is getting calculated as per base quantity(1000 nos.) of BOM header material.

Please suggest what all setting will be required to meet this requirement.

Regards

Blessedgirl

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Aug 14, 2017 at 09:36 AM

    Hi
    Could you please take a look of the below screen shot, where you can understand the concept of Base Qty & Component Quantities
    As shown below, in order to produce 1 PC of Hedaer Material( ST40),
    I need the component Quantiites of : MATR1 >>> 1 PC & MATR2 >>> 1 PC.

    If you need any other Combination, please do the changes in the Change Mode( T code : CS02) for the required Base Qty : & the Component Quantities. Then the system will follow the same , in the Planned Order creation. Also Check your Lot Size of the Finished Materials( in the Material Master >>> MRP1 View)
    For any other details required, please share your BOM Header & component details screen . Thanks & Regards : Raja S Reddy

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Thanks for your input.

      I know that this is standard system behavior.

      I just wanted to know if my requirement can be achieved through any config setting (Not to be done manually) or not.

      I don't want to change the component quantities manually.

      Thanks

      Blessedgirl

  • avatar image
    Former Member
    Aug 14, 2017 at 06:44 PM
    You are confusing with your question.. Can you read your below question

    "In BOM the base quantity for header material(X) is 1000 nos.

    component(A) quantity is 4nos.

    component(B) quantity is 2nos."

    How come planned order Quantity for component is 400 & 200 when your demand is 100 nos for header material?

    To get the above numbers then your BOM should have 4000 & 2000 nos. respectively to make your header material 1000 nos.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Then why don't you setup your BOM as shown below since you know those specific materials -

      Header Material 9188-035 = 1000

      Components
      9190-225 = 4000
      9191-044 = 4000
      9197-817 = 4000
      9007-391 = 2000

      believe me it should work..!