Our client has one reqt ,When network is released in Project System, Single PR is created for one item whereas we want to club all items in one PR.
Pl help me
Thanks
Prasad
SPRO -Project System Structures - Operative Structures Network - Settings for Networks - Specify Parameters for Network Type
Here you will get one indicator for collective PR per order.
You have to select for one PR for all materials.
Hope it will help you.