Hello,

we have problems with some BPM-Processes on our netweaver java system. The BPM-Process is in status completed, but the related BPM-Task is still in status "in Progress". This incorrect state effects, that the BPM-Task is still in the inbox of the user allthoug the BPM-Task is completed. The other bad effect is, that the shedule job "bpm_delete_only" ends in status "Error" and so the other BPM-process which are correct couldn't be deleted.

I tried to delete explicit the instance-id of the bpm-task...the job ended with no error but did not deleted the instance.

Does anybody have an idea how solve/delete this wrong BPM-Task?

Regards

Demetrius Pfoo

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Pfoo Demetrius,

If you face this type issue .you will not able delete the "in-progress" BPM process.You have restart the system .

For permanent fix you can use this SAP Note

OSS Message 462343 / 2019 BPM Process running long.

Hope you will solve this issue .

Thanks & Regards,

Santosh