Compare Task Information in Operative Project & Snapshot Version

Former Member
0 Kudos

Iam working on a BW Report which compares a Task Finish date in Operative Project with Snapshot Task Date. Iam using snapshot as a Baseline for the project.

External ID for task in operative project is different than snapshot

In DPR_Task Table also, the external identifier & GUID is different

Can you pls maention what could be the common reference for both these tasks in tables

warm regards,

Ramakrishna

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Ramakrishna ,

As you may known, the database of the cProject master data is splitted to the CGPL* table and DPR* table. For your case, you can check the table CGPL_COPY_LINK, where the information fo orginal & copied (snapshot for example) guid are stored.

Kind regards,

Zhenbo