on 08-10-2017 9:50 PM
Hello All,
My understanding is that opening date in the planned order is calculated as order start date - opening period from scheduling margin key.
But for one of our client the lead time an GR processing time also inculded.
Could you please explain me the impact of the Planned delivery time in the material master.
I have two examples
Case 1: Planned delivery time not considered
Case 2; Planned delivery time considered
both the cases opening period in the scheduling margin key is 15 days.
Could you throw some light why the system is behaving like this sometimes it is considering the Planned delivery time and sometimes it is not.
Regards,
Sagar
Hi Sagar,
The data that provided is not sufficient to make any analysis /conclusion ( also, it seems data with different settings )
Please find the attached input from your end
Please take a look of the below example, where, I compared two Raw Materials, with the same Scheduling margin Key, but with different Planned Delivery Times. ( Case 1 with 2 Days & Case 2 with 1 Day)
System will consider the Planned Delivery Time, in calculating the Finish date & for Raw materials case, its mandatory field in general
Hope, this might be of some useful info for you. Kindly check & revert back : Thanks & Regards : Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello RAJASEKAHARA REDDY BANNURU
My question is for calculating the Opening date in the order what is the formula?
My understanding is Opening date is calculated as Planned order start date - Opening period from the SMK.
So I want to know that why the system is considering the Planned delivery time also.
I have two cases where in one planned order Planned delivery time is considered and in second planned order the planned delivery time is not considered.
Please help me understand that why the system is behaving like this?
Regards,
Sagar
Hello
My question is for calculating the Opening date in the order what is the formula?
My understanding is Opening date is calculated as Planned order start date - Opening period from the SMK.
So I want to know that why the system is considering the Planned delivery time also.
I have two cases where in one planned order Planned delivery time is considered and in second planned order the planned delivery time is not considered.
Please help me understand that why the system is behaving like this?
Regards,
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sagar,
Thanks for the quick feedback/reply
Yes, your understanding is correct
System Calculates the Dates as follows :
Opening Date = Order Start Date - Opening Period of SMK( Scheduling Margin Key)
Order Finish Date = Order Start Date + Planned Delivery + GR Processing time
Please take a look of the below example with the same scenario
If you need more details, for your cases, Please share the Material Master settings & the SMK Settings & the Planned Order details, for both the Materials, to have the complete understanding of the reported issue. Also, please look into your Factory Calendar dates ( In there any Holidays, during the periods, that you are looking ?? )
Many Thanks for your kind understanding
Best Regards : Raja S Reddy