on 08-11-2017 9:42 AM
Hello, Is there a way to view all raw materials that need to be ordered by MRP Controller? I would like to view them same as I can view all of my production orders in COHV. Thanks
Hi Sarah,
MD06 has the option to restrict by MRP Controller, Date, MRP Type and Procuremnt Type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Transaction - MD05 by choosing tab 'Collective Access'
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.