Hi gurus,

We released a process order, we want to change the component material number because the material enter incorrectly.

But it is not possible to do that because the transfer requirement was already made. So we deleted the Transfer requirement for the warehouse. Then it was still not possible to change the material number.

Any help would be highly appreciated.

Regards,

Tiger

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Thank you all, my client has solved the problem.

Manually create the Transfer Requirement.

Kindly regards,

Tiger

Former Member
0 Kudos

Hi SS,

Thank you for your reply.

That's also I asked my clients to try. I will inform you once they call me.

Regards,

Tiger

Former Member
0 Kudos

Hi Tiger,

What is the error that you are getting while trying to change the material number ??

You can try the following options:

1) Read PP master data again for the process order...this will allow you to change the component materials in Process order

2) after this try to create Transfer requirement (TR) manually for the given Process Order

Try this out and let us know the outcome.