PRODUCTION PLANNING

Is it possble to set rules 'by product' whereby mrp suggested works orders equate to - i.e. 6 weeks worth of product depending on forecasts, to which automatically recalculate as and when forecasts change?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 15, 2017 at 04:58 PM

    Hi Mathew

    I'm not sure if I understood your question.

    The standard MRP procedure PD generates planned orders to cover the forecast and it changes the planned orders when the forecast changes, as long as they are not firmed or converted to production orders.

    Regards,

    Caetano