Hi,

In my businsess a pr was released at x, y levels but the approver has authority to approve at y level only , checked in SU01D, and threads but didnt get find solution, please suggest.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Aug 09, 2017 at 08:14 AM

    Believe me, he either has authority, otherwise he would not have been able to do it. Or your release strategy is wrong setup and already completely released if just the x level is released.

    See Q&A 9 in OSS note 493900 - FAQ: Release Strategy

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 10, 2017 at 01:10 PM

    How you checked in SU01D and validate?

    Talk to S&A team and Business team to find "Release Matrix" to verify users and release codes with each release value of approval.

    Also find what customisation and development carried out for following

    User-1 ------------release code X

    User-2----------------release code Y

    How these are defined and where is control for each/all release code/s on sequential release along with release values are assigned/designed.

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 15, 2017 at 06:40 PM

    hello ,

    it is not possible to release the PO without authorisaiton.

    check the release matrix as well , if the level release codes and release indicators are configured correctly.

    thanks

    kUnal