cProject 4.0 Task Assignment/ Scheduling Changes

Hi All,

My Question is about Task Assignment with the Role Functionality,

Scenario: I have created a Task A with validity Period 08/1/07 - 08/31/07

and than created a Role A with validity Period 08/1/07 - 08/31/07, and than hard booked a resource (Bob) with validity 08/1/07 - 08/31/07 {30 hrs} to the Role A,

Now as a part of Task Assignment I have linked the Role A to the Task A.

Question 1) If the Project Manager now changes the Task A validity Period 08/1/07 - 10/31/07, and does the scheduling in the project ,Is there any way to automatically shift the dates of Role A to 08/01/07 - 10/31/07 and than the Resource to 08/01/07 - 10/31/07,

Question 2) Is there any Mass tool option to change Dates other than the Table view

Hope I made my questions 2 clear,

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 20, 2007 at 10:09 AM

    hi,

    You can change the dates in Graphical view itself by moving the task bar.

    But it is also very cumbersome process.

    regards

    Shiv

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks Shiv for the response,

      You are right, I change Task dates by using the Graphical view, but it will not change the Role Dates, assigned to the Task, as they both are not tied together,

      I wanted to know if there is anyway, i can shift theRoles dates using the Task Date Shifting, other than coding

      Thanks

      Praveen