hi all,

my scenario is related with chemical industry....

example is

for procurement of sulphuric acid the client is having its consumption data of previous year and on the basis of that data client is calculating the requirement for the current year month wise....

how to map ths in SAP ...

is it a part of CBP?

what are the steps required?

sap mm

Accepted Solutions (0)

Answers (1)

Answers (1)

hnmuralidhara
Active Contributor
0 Kudos

Hi,

For this, you have to use Forecast Based MRP type.

To do this, first you have to load historical data for this Plant and Material combination. Then you can use Forecast type based on your business requirements.

Last step, you have to run MRP for this material.