SAP supports two processes for EWM Production Integration.

Option 1: Production Integration (involving inbound and outbound deliveries)

Option 2: Production Integration Advanced (involving EPR and EGR processes).

Can both of these options co exist? My client has implemented option 1 for a specific process industry scenario. Now also want to use option 2 for other scenarios.

Is it possible to use both options in one system?

BR,

Prashant

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 11, 2017 at 07:48 AM

    Hi Prashant,

    2> Production Integration Advanced

    Staging >> In Control cycle, Staging Indicator must be EWM Staging Which will generate PMR( Production Material Request also use for consumption ) .

    Receipts +>> You can use both EPR/EGR and Production/Process order Confirmation or Manual post ( Inbound delivery in EWM ) from ECC.

    Consumption ->> You can post consumption from EWM as well as ECC ( that is Outbound delivery, for update the consumption in PMR, you need do to setting( IMG->SCM Extended Warehouse Management->Extended Warehouse Management->Goods Issue Process->Outbound Delivery->Production Supply->Post Goods Issue for Consumption Posting( Parameter is UPD PMR which will update according to reservation , need to add reservation as ref doc ,Please check the F1 help for that parameter )

    Benefit : Staging,Receipts and Consumption can run in EWM after Production/Process order release from ECC .

    Can both of these options co exist? -> Yes,but Production Integration Advanced will be available in version( >= EWM 9.2 ).

    Is it possible to use both options in one system? As per my knowledge,only Staging will be the difference. PMR in Adv Prod Int. which is outbound delivery/posting change in production integration.Receipts and Consumption can be the same.->Please check the link for more details Advanced Production Integration.

    Please let us know if you have further queries.

    Kind Regards,

    Ajit

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Prashant,

      Staging will be the only difference.

      "Delivery based integration is already in place that is Outbound Delivery for Staging ( triggers at order release)" - you need a new control cycle ( Plant+PSA( New ) +Material-optional ) for PMR ( Staging -EWM Staging ). PSA assign to Production Work center or material...etc.

      Please check the link for difference and answer to your doubt.Overview of Production Integration Types