cProjects 3.1: Changing calendar does not recalculate durations and dates

Former Member
0 Kudos

Hi Guys,

I have not set a calendar at the project definition in level in the cprojects structure. I have set dates and durations for tasks and stages. Since I have not specified a calendar the calculated dates and durations consider all days including weekends. If I now specify a calendar which is defined to have 5 day work week, the calculated date and durations are not updated. Any ideas? I would like to avoid manually making changes to each and every task so that new calendard takes effect.

Thanks...

Lashan

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

Hi Lashan,

The note 802377 solve this problem, but it can be only applied using hotpackage.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Zhenbo,

Thanks for the reply. We are on patch level 9, so the fixes for this is already in. I tested the issue mentioned in the OSS note and it is working fine in our system. I can change the calendar at task or phase level and the durations/dates are calculated correctly.

The issue I am facing is that the calendar is defined in the project definition. For phases and tasks I have specified "use from project". When I change in the project definition level, this change is not reflected in the phases or tasks below.

Am I missing something?

Cheers,

Lashan

former_member201206
Active Contributor
0 Kudos

Hi Lashan,

I could not find any relevant note, though the problem is solved in SAP internal system. May be it is related to the status of the object, is it released?

If the problem persists, you can open a customer message to let SAP check it.

Kind regards,

Zhenbo

Former Member
0 Kudos

Thanks Zhenbo, will do further testing and log a message.

I've tried on tasks with status released as well as created, same result (even after clicking schedule when testing released tasks/phases).

Cheers,

Lashan

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Lashan,

Once you release the project automatic scheduling will not happen in cProjects. After assigning the calander you have to press the schedule button. Then system will rescedule all the tasks. And one more thing is you have to give duration and days. If you maintain dates it will consider the dates only it will not reschedule automatically.

Thanks

Venkat Bandaru