Skip to Content
avatar image
Former Member

cProjects 3.1: Changing calendar does not recalculate durations and dates

Hi Guys,

I have not set a calendar at the project definition in level in the cprojects structure. I have set dates and durations for tasks and stages. Since I have not specified a calendar the calculated dates and durations consider all days including weekends. If I now specify a calendar which is defined to have 5 day work week, the calculated date and durations are not updated. Any ideas? I would like to avoid manually making changes to each and every task so that new calendard takes effect.

Thanks...

Lashan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 08, 2007 at 11:57 AM

    Hi Lashan,

    Once you release the project automatic scheduling will not happen in cProjects. After assigning the calander you have to press the schedule button. Then system will rescedule all the tasks. And one more thing is you have to give duration and days. If you maintain dates it will consider the dates only it will not reschedule automatically.

    Thanks

    Venkat Bandaru

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 08, 2007 at 11:46 AM

    Hi Lashan,

    The note 802377 solve this problem, but it can be only applied using hotpackage.

    Kind regards,

    Zhenbo

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Zhenbo Wang

      Thanks Zhenbo, will do further testing and log a message.

      I've tried on tasks with status released as well as created, same result (even after clicking schedule when testing released tasks/phases).

      Cheers,

      Lashan