Assembly processing in the project system

Hi,

Can any body explain me how to meet the below requirement:

The requirement is to create one WBS for each sales document item with different material number in a same sales order .

Rgds,

Prasad

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    author's profile photo
    Former Member
    Posted on Aug 08, 2007 at 12:32 PM

    Hi Raghavendra,

    You can do this by maintaining all the materials assigned in sales order to single standard WBS. Then when you do the sales order one single WBS structure will be created.

    Rgds,

    Pradeep

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Prasad,

      1. Created standard WBS first.

      2. Created standard network from standard WBS.

      3. Create material master. Ensure strategy group & Item category group is properly maintained in material master.

      3. In CN08,allocate material created to standard network.

      Please ensure that you assign following things here.

      Material number-Order type-Standard network-Network profile-MRP Controller for the order-Standard WBS element

      While creating sales order,give sales order type as PS1.

      Please check this & try.

      For more info please refer the link below.

      http://help.sap.com/saphelp_46c/helpdata/en/95/1613a8837b11d2b6700000e82d8bd1/frameset.htm

      Regards

      Tushar