Planned order is not showing exception message 05 in MD04 though the vendor has RLT of 84 days

Hello All,

I have one query I am not getting exception message 05 (Start date is in past) for a planned order in MD04 for a specific material. The vndoe has RLT of 84 days.

I don't know how RLT and all plays the role in MD04.

Also I don't know much about MD04 dates calculations.

Kindly let me know possible reasons for this.

Also let me know what where should I look into to find the root cause.

Regards,

Sagar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 08, 2017 at 03:32 AM

    md04.pngmd12.pngmd-12.png

    I have attached MD04 and MD12 screenshots also I checked that the scheduling margin key has 15 days of the opening period.So in planned order planned opening date and order start date has 15 days difference. Please let me know what I am missing. Where and how the exception message should appear as " Start date is in past".

    Please let me know.

    Regards,

    Sagar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Let me make my statement clear -

      If the planned order 'Opening date' is in the past than system current date you will get the exception message '05'

      Change the 'Opening date' to 07/08/2017 instead of 09/08/2017 then you will see the exception '05'

  • Aug 07, 2017 at 03:08 PM

    start date in past in customizing is not maintained in OPPQ or in OPPR. Please check.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 07, 2017 at 02:14 PM

    If the planned order 'Opening date' is in the past then you will get the exception message '05'. It is a system standard message where you don't have configuration.

    You can go to transaction MD12 and change the planned order 'Opening date' then you will see the message '05' (Keep 'start date' is current date).

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Sagar,

      The dates would be calculated based on your requirements vs your receipts. Per instance, if the requirement falls before the receipt then system will give the exception message '15' (Reschedule out).

      The exception messages are triggered after MRP run. In addition, these messages are nothing to do with material master or Configuration setup...

      Thanks,
      Srini