Process order with wbs assignement.

Aug 04, 2017 at 02:55 PM

74

avatar image
Former Member

Dear All

How to create process order with WBS account assignement similar to CO10 transaction.

Want to have project stock after process order Goods receipt.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Caetano Almeida
Aug 07, 2017 at 06:53 PM
0

Hello

Usually, those orders are created by the conversion of planned orders generated by MRP. You can generate a reservation on your project and execute MRP to create planned orders.

Regards,

Caetano