on 08-07-2017 9:15 AM
Hallo,
is there a solution for this scenario:
Best regards,
Klaus Hoffmann
Hi Klaus,
I think the worker can enter the resource during the confirmation of the task.
After entering the time spent on the activity, the system should allow the "add row" option in the Resources section (all under the Activities tab).
There the user can enter a different resource. He/She will not be able to remove the original resource however as long as the time entered against it is zero, the system should understand it as "not used".
Best regards!
Rodrigo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rodrigo,
I will test
Thanks
Klaus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.