Production flexibility in ByD

Klaus01
Participant
0 Kudos

Hallo,

is there a solution for this scenario:

  1. Single equipment is configured - no ressource groups
  2. In the production model only single ressources are used (no ressource groups)
  3. the production order has been released
  4. The planned ressource fails; there is nobody to replan; the worker uses a different ressource for production and wants to commit his work/release the production order.

Best regards,

Klaus Hoffmann

Accepted Solutions (1)

Accepted Solutions (1)

Hi Klaus,

I think the worker can enter the resource during the confirmation of the task.

After entering the time spent on the activity, the system should allow the "add row" option in the Resources section (all under the Activities tab).

There the user can enter a different resource. He/She will not be able to remove the original resource however as long as the time entered against it is zero, the system should understand it as "not used".

Best regards!

Rodrigo

Answers (1)

Answers (1)

Klaus01
Participant
0 Kudos

Hi Rodrigo,

I will test

Thanks

Klaus