Does a No remaining work flag on a operation/activity have a finish date associtaled with it.

I can get actual start date with an initial confirmation. But I am curious as to if there is there any actual finish date field associated with a "no remaining work" flag. We would like to run KPI's off of this instead of a CNF due to its inconsistent use. I can control the no remaining work flag for the field.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 06, 2017 at 06:56 AM

    Hi Jason,

    1. You have a field for Work Start and Finish in the confirmation

    May be if they fill, this can be useful to take it.

    2. Also in Table AFRU, there is a date field for Entered by, this will be filled based on the day confirmation is getting created.

    Regards

    Terence