Does a No remaining work flag on a operation/activity have a finish date associtaled with it.

Aug 05, 2017 at 01:18 AM


avatar image

I can get actual start date with an initial confirmation. But I am curious as to if there is there any actual finish date field associated with a "no remaining work" flag. We would like to run KPI's off of this instead of a CNF due to its inconsistent use. I can control the no remaining work flag for the field.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Aug 06, 2017 at 06:56 AM

Hi Jason,

1. You have a field for Work Start and Finish in the confirmation

May be if they fill, this can be useful to take it.

2. Also in Table AFRU, there is a date field for Entered by, this will be filled based on the day confirmation is getting created.