What is meant by RefID in default values of Workcentre ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Patil,

The RefID in the default values of the workcentre is used to freeze the particular value when you call that work centre in a task list. Meaning if this indicator is ticked in the WC creation,during your creation or change of a task list, the values will automatically get copied against that work centre and it will not allow the user to change that value.

reg

Kiki

Award points if this helps

Answers (3)

Answers (3)

former_member184627
Active Contributor
0 Kudos

Hi,

For eg: In t.code cr02 for work center enter the control key as pp01 in default values tab & then tick the REFID indicator.

Then create a routing & enter the work center, the control key will be copied & will be in display (grey) mode, you cannot change it.

In cr02 remove the REFID indicator & then create a routing, now you can change the control key from pp01 to pp02.

Regards,

SDS

Former Member
0 Kudos

Hi

If you check this in workcenter the values will be copied to routing and cannot be changed in routing

Can be changed only in WC

Regards

Ranga

Former Member
0 Kudos

Hi,

This setting is useful for default settings in routings for control key etc.

If u set it for indicator system will not allow to change this setting in routing. It will be grayout.

It is for security purpose. If u want any changes u have to chage it in work cnter only.In routing it will not allowed.