Hi All,

Am I correct in saying that in Easy Cost Planning when entering costs a cost element needs to be assigned. If so how is this done. I have created the costing model. My last company had it set up so that the planned costs from ECP could be seen in reports like S_ALR_87013542.

Thanks

Stuart

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Stuart,

In OKTZ you

a) have a cost component structure with cost components, like raw materials, production, production overhead etc.

b) assign cost elements (ranges) to the cost components

c) assign the costing variant to the cost component structure

that should solve your problem.