error in c project accounting

former_member214272
Contributor
0 Kudos

Dear plm consultant,

I am facing problem in c project costing . when i go for calulate the cost, i get following error.

<b>Error occurred in accounting - see controlling cockpit (cProjects)

Message no. DPR_FIN_GECCO024</b>

Diagnosis

Errors occurred when transferring to accounting.

System Response

DPR_FIN_GECCO 024

Procedure

Choose the link on the Accounting tab page. In the cockpit, you can create a variant with your cProjects project under Selection Variant Orders cProjects . The errors that occurred are then displayed. If no messages are displayed in the controlling cockpit, they have already been processed or deleted. If this is the case, trigger the transfer again.

No more messages are displayed once the transfer has been carried out successfully (that is, no errors occurred).

i am unable to trace the problem,help me for same

point will be reward for answer

thanx

sunil jawalkar

suniljawalkar@hotmail.com

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member214272
Contributor
0 Kudos

solve

former_member845166
Active Participant
0 Kudos

hi sunil,

Can you please share hove you solved this error.

if any docs are presend pls share it at shivshankar1683@hotmail.com

regards

Shiv

former_member214272
Contributor
0 Kudos

hi shivshankar,

there is option on accounting tab page controlling cocpit you click on them.

then thruogh ITS it go to your r/3 system there you make nessary settings

thnax

sunil jawalkar