Hallo, SAP'ers!
I'm gonna execute Material cost estimate with quantity structure (<b>CK11N</b>)
I use my own cost component structure with it's own cost components(created by copying several of them from the standard one). I assigned cost elements to these cost components
using <i>Assignment: Organiz. Units - Cost Component Struct</i> I assigned created by me cost component structure to my company code.
the structure is activated.
when I process <b>CK11N</b>, only data in "Raw materials" component are displayed which is taken from material master record of the calculating material.
where can I enter planned data for every cost element in order this data is calculated and displayed for every cost component to which according cost elements are assigned?
Step-by-step recommendations in customizing will be very helpful and rewarded.
Thanks!