i have confirmed the TO and materials are in our dynamic location PSA but now my BOM is changed and now i want to reflect that changes in my production order, so as a normal process i tried PP run but got the error message that transport requirement generated. How to reflect those changes in current production order.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 01, 2017 at 02:41 PM

    please refer sap KBA. Confirmed transfer order cannot be cancelled by LT15. read PP master data will also not work error will be thrown.

    73765 - Change in quantity in WM-PP interface

    Add comment