Alternate BOM

Former Member
0 Kudos

Dear all,

How to use Alternate BOM ? How to give priority for the stocks availability of semifinshed material for finished material mentioned in BOM.

e.g. finished material - RA0100GR000- Local requirement

For this we use Blanks ( SEmifinished ) --- DA0100GRL00 (Local),

DA0100GRE00 (EXPORT),

We have made Alternate BOM for RA0100GR000.

How to decide Priority for Blanks availabilty for the above material ?

We use first Local to local. But if it is not available in stock then we use Export blanks.

How to map this ?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In BOM alternative items are assigned to alternative item group on the general data.

In the production order in the general data tab page.

We can define the alternative item based on priority , strategy and usage probability.

Priority:

This defines the priority of the item within the alternative item group.

This determines the priority of planned withdrawls of items.

EX Two items are assigned to alternative item group

item A Priority 1

item B Priority 2

The system reads the item A first.

Strategy:

use the strategy to determine how the planned withdrawl is controlled

within the alternative item group.

The strategy should be same for all alternative items within a alternative

item group.

If the value 2( 100% check) is defined for the strategy the first material in

the defined priority sequence for which sufficient quantities are available

are reserved.

Usage Probability:

MRP Plans these alternative material components according to probability

of use.Material requirements for BOM Components are planned according

to usage probability.

The planned withdrawls for the production order are based on the

reservation lists.These lists are based on the priority and strategy.

Regards,

nandha

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi kishore,

dont use alternate BOM

this type os case its always use alternative item group , you can see in CS01 and go to item detail in that you can see alternative item group

use this it will solve your problem

reward me if its solve your problem

Thanks