Skip to Content
0
Former Member
Jul 27, 2007 at 02:56 PM

Planned Order Reduction

89 Views

Hi everybody,

I have a problem when reducing planned orders. In Rep. Man. Profile, reduction period is 7 days. I want MFBF confirmations reduce only Planned Orders in current week. Since we define the period 7 days, when production overs the plan and posting day is different from Monday of the current week, our confirmation reduces the planned orders of next week. So, I need some way to change this customizing parameter dynamically to limit the effect on next week.

Any suggestion?

Thanks,

Lokman Ceylan